Draft Chapter 1 - Overview Mar 9, 2017
      17OVE001 - MOC Fish Impacts Feb 16, 2017  APPROVED
      17OVE002 - MOC Responsibilities Mar 9, 2017  APPROVED
      17OVE003 - FPOM Coordination Sep 14, 2017  APPROVED*
Draft Chapter 2 - Bonneville Dam Mar 9, 2017
      17BON001 - Lamprey Operations Start Date Jul 15, 2016  NOT APPROVED
      17BON002 - Kelt Trigger Clarification Jul 15, 2016  APPROVED
      17BON003 - Nighttime Lamprey Operations Jan 23, 2017  WITHDRAWN
      17BON004 - Ladder Temperature Monitoring Mar 9, 2017  APPROVED
      17BON005 - Oil Spill Response Feb 1, 2017  APPROVED
      17BON006 - SLEDs Feb 1, 2017  APPROVED
      17BON007 - Turbine Operating Range Feb 1, 2017  APPROVED
      17BON008 - Delete PH2 Mid-Range Operation Mar 9, 2017  APPROVED
Draft Chapter 3 - The Dalles Dam Mar 9, 2016
      17TDA001 - Oil Spill Response Feb 1, 2017  APPROVED
      17TDA002 - Ladder Temperature Monitoring Feb 1, 2017  APPROVED
      17TDA003 - Turbine Operating Range Feb 1, 2017  APPROVED
      17TDA004 - Sluiceway March Unit Priority Mar 9, 2017  APPROVED
      17TDA005 - Sluiceway Involuntary Spill Mar 9, 2017  APPROVED
      17TDA006 - Single Fish Unit Operation May 11, 2017  APPROVED*
Draft Chapter 4 - John Day Dam Feb 16, 2017
      17JDA001 - Daytime Spill Hours Clarification May 12, 2016  APPROVED
      17JDA002 - Ladder Temperature Monitoring Feb 1, 2017  APPROVED
      17JDA003 - Turbine Operating Range Feb 1, 2017  APPROVED
      17JDA004 - Oil Spill Response Feb 1, 2017  APPROVED
      17JDA005 - Gatewell Dipping July 13, 2017  APPROVED*
Draft Chapter 5 - McNary Dam Feb 16, 2017
      17MCN001 - Updated Spill Patterns w/ No TSWs Dec 8, 2016  APPROVED
      17MCN002 - Fishway Temperature Monitor Map Feb 1, 2017  APPROVED
      17MCN003 - Turbine Unit Operating Range Feb 1, 2017  APPROVED
      17MCN004 - Unit Priority Winter Maintenance Feb 1, 2017  APPROVED
      17MCN005 - Oil Spill Response Feb 1, 2017  APPROVED
      17MCN006 - Count Station Pickets May 11, 2017  APPROVED*
      17MCN007 - Table MCN-7 High Flow Spill Patterns May 11, 2017  APPROVED*
      17MCN008 - Table MCN-10 High Flow Spill Patterns Jun 8, 2017  APPROVED*
Draft Chapter 6 - Ice Harbor Dam Feb 16, 2017
      17IHR001 - RSW Low Flow Clarification Feb 1, 2017  APPROVED
      17IHR002 - Fishway Temperature Monitor Map Feb 1, 2017  APPROVED
      17IHR003 - Operational Testing Feb 16, 2017  APPROVED
      17IHR004 - Turbine Unit Operating Range Feb 1, 2017  APPROVED
      17IHR005 - Oil Spill Response Feb 1, 2017  APPROVED
      17IHR006 - Count Station Pickets May 11, 2017  APPROVED*
      17IHR007 - Unit 5 Fixed-Blade Range May 11, 2017  APPROVED*
Draft Chapter 7 - Lower Monumental Dam Feb 16, 2017
      17LMN001 - Fishway Temperature Monitor Map Feb 1, 2017  APPROVED
      17LMN002 - Turbine Unit Operating Range Feb 1, 2017  APPROVED
      17LMN003 - Unit Priority Winter Maintenance Feb 1, 2017  APPROVED
      17LMN004 - RSW Low Flow Clarification Feb 1, 2017  APPROVED
      17LMN005 - Oil Spill Response Feb 1, 2017  APPROVED
      17LMN006 - Count Station Pickets May 11, 2017  NOT APPROVED
Draft Chapter 8 - Little Goose Dam Feb 16, 2017
      17LGS001 - SW Close Criteria  [Attachment 1] May 12, 2016  NOT APPROVED
      17LGS002 - Unit 5 Priority Feb 1, 2017  APPROVED
      17LGS003 - Turbine Unit Operating Range Feb 1, 2017  APPROVED
      17LGS004 - Fishway Temperature Monitor Map Feb 1, 2017  APPROVED
      17LGS005 - Oil Spill Response Feb 1, 2017  APPROVED
      17LGS006 - Count Station Pickets May 11, 2017  NOT APPROVED
      17LGS007 - Position of Operating Gates July 13, 2017  APPROVED*
Draft Chapter 9 - Lower Granite Dam Feb 16, 2017
      17LWG001 - Forebay Exit Cooling Pumps Feb 1, 2017  APPROVED
      17LWG002 - Fishway Temperature Monitor Map Feb 1, 2017  APPROVED
      17LWG003 - Channel Velocity Feb 1, 2017  APPROVED
      17LWG004 - Turbine Unit Operating Range Feb 1, 2017  APPROVED
      17LWG005 - AWS Oil Operation Feb 1, 2017  APPROVED
      17LWG006 - RSW Low Flow Clarification Feb 1, 2017  APPROVED
      17LWG007 - Count Station Pickets May 11, 2017  APPROVED*
      17LWG008 - U1, U2 Priority Sep 14, 2017  APPROVED*
Appendix A - Special Ops & Studies Feb 16, 2017
      17AppA001 - Doble Testing Schedule Feb 1, 2017  APPROVED
Appendix B - Transportation Plan Nov 16, 2016
      17AppB001 - Revised Fleet Size May 12, 2016  APPROVED
      17AppB002 - Transition to Primary Bypass Nov 16, 2016  APPROVED
Appendix C - BPA Load Shaping Guidelines Aug 1, 2016
Appendix D - Ops for Non-Listed Species Feb 13, 2017
      17AppD001 - MCN Lamprey Passage Apr 14, 2016  APPROVED
      17AppD002 - MCN Lamprey Plating Removal Feb 13, 2017  APPROVED
Appendix E - Fish Operations Plan (FOP) Comments via RIOG
Appendix F - Dewatering Fish Salvage Aug 1, 2016
Appendix G - Adult Trap Ops BON, IHR, LWG Aug 1, 2016
Appendix H - CHJ Turbine Dewatering Aug 1, 2016
Appendix I - DWR Turbine Maintenance Aug 1, 2016
      17DWR001 - New DWR O&M Section Moved to 18DWR001
Appendix J - Smolt Facility Ops BON, JDA, MCN Aug 1, 2016
Appendix K - Acronyms Aug 1, 2016
Appendix L - Avian Plans Aug 1, 2016
 
Fish Passage Plan Homepage