Draft 2020 Fish Passage Plan (FPP)
& Change Forms

* Change Forms approved after March 1, 2020, are NOT included in the print version of the 2020 FPP.

Draft Project-Specific Chapters
Edits shown in Track Changes
Change Forms Posted Change Form
Status
Draft Chapter 1 - Overview 20OVE001 - Update BiOp 24-JAN-2020  APPROVED
Draft Chapter 2 - Bonneville Dam 20BON001 - Ladder Temperature Monitoring 13-FEB-2020  WITHDRAWN
20BON002 - PH2 Mid-Range Spill 13-FEB-2020  APPROVED
20BON003 - Reduced Nighttime Flow 12-MAR-2020  WITHDRAWN
Draft Chapter 3 - The Dalles Dam 20TDA001 - AWS Operation 24-JAN-2020  APPROVED
20TDA002 - Avian Abatement 30-JAN-2020  APPROVED
20TDA003 - ITS Operation 24-JAN-2020  APPROVED
20TDA004 - Picket Seating 30-JAN-2020  APPROVED
20TDA005 - AWS With One FU 30-JAN-2020  APPROVED
20TDA006 - ITS U1 and U18 30-JAN-2020  APPROVED
20TDA007 - Outage Schedule 30-JAN-2020  APPROVED
20TDA008 - Spillbay 9 Footnote 30-JAN-2020  APPROVED
20TDA009 - Reduced Nighttime Flow 12-MAR-2020  WITHDRAWN
20TDA010 - Dewater Below Tailwater * 17-NOV-2020 *  APPROVED
Draft Chapter 4 - John Day Dam 20JDA001 - Remove March 1 Bypass Start 24-JAN-2020  APPROVED
20JDA002 - Range for Locked-Blade Units 13-FEB-2020  APPROVED
20JDA003 - TSW Installation 8-OCT-2020  WITHDRAWN
Draft Chapter 5 - McNary Dam 20MCN001 - March 1 Bypass Start 24-JAN-2020  APPROVED
20MCN002 - Automated Temperature Monitoring 30-JAN-2020  WITHDRAWN
20MCN003 - Range for Locked-Blade Units 13-FEB-2020  APPROVED
Draft Chapter 6 - Ice Harbor Dam 20IHR001 - Turbine Ranges 24-JAN-2020  APPROVED
20IHR002 - Automated Temperature Monitoring 30-JAN-2020  WITHDRAWN
20IHR003 - Operating Gates Position 10-NOV-2020  WITHDRAWN
Draft Chapter 7 - Lower Monumental Dam 20LMN001 - Operating Gates Position 4-FEB-2020  APPROVED
20LMN002 - Remove March 1 Bypass Start 24-JAN-2020  APPROVED
20LMN003 - Automated Temperature Monitoring 30-JAN-2020  WITHDRAWN
20LMN004 - Units 4, 5 Locked Blades 4-FEB-2020  APPROVED
20LMN005 - Range for Locked-Blade Units * 17-MAR-2020 *  APPROVED
20LMN006 - Units 2, 4, 5 Priority Order * 11-JUN-2020 *  APPROVED
Draft Chapter 8 - Little Goose Dam 20LGS001 - ESBS Cleaning Brushes 30-JAN-2020  APPROVED
20LGS002 - ESBS Unscheduled Maintenance 30-JAN-2020  APPROVED
20LGS003 - Surface Velocity 13-FEB-2020  APPROVED
20LGS004 - ASW Updates 4-FEB-2020  APPROVED
20LGS005 - Automated Temperature Monitoring 30-JAN-2020  WITHDRAWN
Draft Chapter 9 - Lower Granite Dam 20LWG001 - March 1 Bypass Start 24-JAN-2020  APPROVED
20LWG002 - Automated Temperature Monitoring 30-JAN-2020  WITHDRAWN
20LWG003 - Range for Locked-Blade Units 13-FEB-2020  APPROVED
20LWG004 - Higher Spring Spill Patterns * 11-JUN-2020 *  APPROVED
Draft Appendices
All approved changes shown in Track Changes
Change Forms Posted* Change Form
Status
Draft Appendix A - Special Ops & Studies 20AppA001 - Doble Test Schedule 4-FEB-2020  APPROVED
20AppA002 - Spill for Steelhead Overshoots 10-SEP-2020  APPROVED
Draft Appendix B - Transport Plan 20AppB001 - Transport Updates 4-FEB-2020  APPROVED
20AppB002 - Additional Transport Truck * 11-JUN-2020 *  APPROVED
Draft Appendix C - BPA Load Shaping Guidelines none --- ---
Draft Appendix D - Ops for Non-Listed Species none --- ---
Draft Appendix E - Fish Operations Plan (FOP) N/A (coordinated via RIOG) --- ---
Draft Appendix F - Dewatering Fish Salvage 20AppF001 - Sturgeon Coordination 14-JAN-2021  APPROVED
Draft Appendix G - Adult Trap Ops BON, IHR, LWG 20AppG001 - Adult Trap Water Supply 13-FEB-2020  APPROVED
20AppG002 - Adult Trap Water Temperatures 26-FEB-2020  APPROVED
20AppG003 - LWG Trap Dewatering * 8-OCT-2020 *  APPROVED
Draft Appendix H - CHJ Turbine Dewatering none --- ---
Draft Appendix I - DWR Turbine Maintenance none --- ---
Draft Appendix J - Smolt Facility Ops BON, JDA, MCN 20AppJ001 - MCN March 1 Start 4-FEB-2020  APPROVED
20AppJ002 - JDA Index Sampling * 9-APR-2020 *  APPROVED
Draft Appendix K - Acronyms none --- ---
Draft Appendix L - Avian Plans 20AppL001 - Table 1 Hazing Schedule 4-FEB-2020  APPROVED
20AppL002 - BON SLEDs 4-FEB-2020  APPROVED
20AppL003 - MCN 4-FEB-2020  APPROVED
20AppL004 - IHR 4-FEB-2020  APPROVED
20AppL005 - LGS 4-FEB-2020  APPROVED
20AppL006 - LWG 4-FEB-2020  APPROVED
20AppL007 - TDA 4-FEB-2020  APPROVED
 
Fish Passage Plan Homepage