Draft 2018 Fish Passage Plan (FPP)
& Change Forms
* Change Forms approved after March 1, 2018, are NOT included in print versions of the 2018 FPP.
Draft Project-Specific Chapters
All approved changes shown in Track Changes
Change Forms
Posted
Change Form
Status
Draft Chapter 1 - Overview
18OVE001 - State TDG Terminology
1/11/2018
APPROVED
18OVE002 - Spill Pattern Dates
2/8/2018
APPROVED
Draft Chapter 2 - Bonneville Dam
18BON001 - Table BON-5 Correction
9/14/2017
APPROVED
18BON002 - Add Turbine Operating Limit
2/12/2018
APPROVED
18BON003 - Diffuser Cleaning
*
5/24/2018*
APPROVED
18BON004 - Chiller Discharge
*
6/14/2018*
APPROVED
18BON005 - Unit Priority Change
*
6/14/2018*
APPROVED
Draft Chapter 3 - The Dalles Dam
18TDA001 - Add Turbine Operating Limit
2/12/2018
APPROVED
18TDA002 - PUD Outage Time
*
6/14/2018*
APPROVED
Draft Chapter 4 - John Day Dam
18JDA001 - March 1 Bypass Start
1/11/2018
APPROVED
18JDA002 - Minimum Spill Correction
1/11/2018
APPROVED
18JDA003 - Add Turbine Operating Limit
2/12/2018
APPROVED
Draft Chapter 5 - McNary Dam
18MCN001 - Work Near Fishway
9/6/2018
Moved to 2019
18MCN002 - Add Turbine Operating Limit
2/12/2018
APPROVED
18MCN003 - ESBS Schedule
*
3/20/2018*
APPROVED
Draft Chapter 6 - Ice Harbor Dam
18IHR001 - AWS High Tailwater
9/14/2017
APPROVED
18IHR002 - Work Near Fishway
9/6/2018
Moved to 2019
18IHR003 - Unit 2 Priority
1/11/2018
APPROVED
18IHR004 - Ladder Exit Criteria
1/11/2018
APPROVED
18IHR005 - Add Turbine Operating Limit
2/12/2018
APPROVED
Draft Chapter 7 - Lower Monumental Dam
18LMN001 - Table LMN-11
10/14/2017
APPROVED
18LMN002 - Work Near Fishway
9/6/2018
Moved to 2019
18LMN003 - Update Units 1-4
2/8/2018
APPROVED
18LMN004 - Add Turbine Operating Limit
2/12/2018
APPROVED
Draft Chapter 8 - Little Goose Dam
18LGS001 - March 1 Bypass Start
1/11/2018
APPROVED
18LGS002 - Work Near Fishway
9/6/2018
Moved to 2019
18LGS003 - Orifice Checks
1/26/2018
APPROVED
18LGS004 - Differentials
1/11/2018
APPROVED
18LGS005 - North Unit Priority Order
2/14/2018
APPROVED
18LGS006 - Add Gas Cap Spill Patterns
2/14/2018
APPROVED
18LGS007 - ASW Updates
2/14/2018
APPROVED
18LGS008 - Add Turbine Operating Limit
2/12/2018
APPROVED
18LGS009 - Fish Pump Criteria
*
6/18/2018*
APPROVED
18LGS010 - ASW Criteria
*
9/13/2018*
APPROVED
Draft Chapter 9 - Lower Granite Dam
18LWG001 - Work Near Fishway
9/6/2018
Moved to 2019
18LWG002 - Updates for Units 1-2
2/8/2018
APPROVED
18LWG003 - Add Turbine Operating Limit
2/12/2018
APPROVED
18LWG004 - Position of Operating Gates
*
6/14/2018*
APPROVED
18LWG005 - JBS Upgrade
*
6/14/2018*
APPROVED
Draft Appendices
All approved changes shown in Track Changes
Change Forms
Posted*
Change Form
Status
Draft Appendix A - Special Ops & Studies
18AppA001 - Doble Testing Schedule
1/11/2018
APPROVED
Draft Appendix B - Transport Plan
18AppB001 - March 1 LGS Bypass Start
1/11/2018
APPROVED
18AppB002 - LMN Transport
1/11/2018
APPROVED
Draft Appendix C - BPA Load Shaping Guidelines
Draft Appendix D - Ops for Non-Listed Species
18AppD001 - Cooling Strainer Inspections
9/14/2017
APPROVED
Draft Appendix E - Fish Operations Plan (FOP)
N/A (coordinated via RIOG)
Draft Appendix F - Dewatering Fish Salvage
Draft Appendix G - Adult Trap Ops BON, IHR, LWG
18AppG001 - JBS Upgrade
*
6/14/2018*
APPROVED
Draft Appendix H - CHJ Turbine Dewatering
Draft Appendix I - DWR Turbine Maintenance
Draft Appendix J - Smolt Facility Ops BON, JDA, MCN
Draft Appendix K - Acronyms
Draft Appendix L - Avian Plans
18AppL001 - LGS Avian Plan
1/11/2018
APPROVED
Fish Passage Plan Homepage