Green Peter Dam
Wednesday April 17, 2024
Hour | Total Outflow cfs | Generation Flow cfs | Spill cfs | Forebay Elevation | Tailwater Elevation | Average Head |
1 | 1270 | | | 987.17 | 697.86 | 289.31 |
2 | 1270 | | | 987.17 | 697.90 | 289.27 |
3 | 1270 | | | 987.15 | 697.82 | 289.33 |
4 | 1270 | | | 987.14 | 697.82 | 289.32 |
5 | 1270 | | | 987.12 | 697.83 | 289.29 |
6 | 1270 | | | 987.11 | 697.84 | 289.27 |
7 | 1270 | | | 987.10 | 697.89 | 289.21 |
8 | 1270 | | | 987.09 | 697.87 | 289.22 |
9 | 1270 | | | 987.07 | 697.92 | 289.15 |
10 | 1270 | | | 987.05 | 697.82 | 289.23 |
11 | 1270 | | | 987.04 | 697.80 | 289.24 |
12 | 1270 | | | 987.02 | 697.78 | 289.24 |
13 | 1270 | | | 987.00 | 697.82 | 289.18 |
14 | 1270 | | | 986.99 | 697.90 | 289.09 |
15 | 1270 | | | 986.98 | 697.91 | 289.07 |
16 | 1270 | | | 986.97 | 697.92 | 289.05 |
17 | 1270 | | | 986.95 | 697.86 | 289.09 |
18 | 1270 | | | 986.94 | 697.80 | 289.14 |
19 | 1270 | | | 986.92 | 697.79 | 289.13 |
20 | 1270 | | | 986.91 | 697.77 | 289.14 |
21 | 1270 | | | 986.89 | 697.81 | 289.08 |
22 | 1270 | | | 986.88 | 697.78 | 289.10 |
23 | 1270 | | | 986.86 | 697.80 | 289.06 |
24 | 1270 | | | 986.85 | 697.80 | 289.05 |
|
AVG | 1270 | | | 987.02 | 697.84 | 289.18 |
|
MAX | 1270 | | | 987.17 | 697.92 | 289.33 |
MIN | 1270 | | | 986.85 | 697.77 | 289.05 |