US Army Corps of Engineers

Dexter Dam

Saturday May 28, 2022

New Date:

HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 1627 692.47 637.27 55.20
2 1640 692.49 637.30 55.19
3 1627 692.51 637.32 55.19
4 1627 692.53 637.31 55.22
5 1614 692.55 637.33 55.22
6 1627 692.57 637.29 55.28
7 1627 692.47 637.29 55.18
8 1627 692.37 637.33 55.04
9 1627 692.24 637.31 54.93
10 1627 692.11 637.34 54.77
11 1614 691.98 637.32 54.66
12 1601 691.85 637.29 54.56
13 1601 691.72 637.28 54.44
14 1614 691.59 637.29 54.30
15 1601 691.69 637.29 54.40
16 1640 691.83 637.30 54.53
17 1614 691.98 637.29 54.69
18 1614 692.13 637.28 54.85
19 1614 692.26 637.30 54.96
20 1627 692.44 637.29 55.15
21
22
23
24
AVG 1620   692.19 637.30 54.89
MAX 1640   692.57 637.34 55.28
MIN 1601   691.59 637.27 54.30