Hour | Total Outflow kcfs | Generation Flow kcfs | Spill kcfs | PH 1 Forebay Elevation | Tailwater Elevation | Average Head | Project Forebay Elevation | Stevenson Gage Elevation | Project Tailwater Elevation |
1 | 148.30 | 126.90 | 9.00 | 74.30 | 13.30 | 61.00 | 74.20 | 74.90 | 13.40 |
2 | 151.00 | 128.00 | 10.60 | 74.10 | 13.40 | 60.70 | 74.00 | 74.70 | 13.50 |
3 | 150.70 | 127.50 | 10.80 | 74.10 | 13.30 | 60.80 | 74.00 | 74.70 | 13.40 |
4 | 151.10 | 127.90 | 10.80 | 74.10 | 13.30 | 60.80 | 74.00 | 74.70 | 13.40 |
5 | 150.90 | 127.70 | 10.80 | 74.00 | 13.30 | 60.70 | 73.90 | 74.60 | 13.40 |
6 | 151.40 | 128.20 | 10.80 | 73.80 | 13.40 | 60.40 | 73.80 | 74.50 | 13.40 |
7 | 151.50 | 128.30 | 10.80 | 74.00 | 13.50 | 60.50 | 73.90 | 74.50 | 13.60 |
8 | 151.10 | 127.90 | 10.80 | 74.40 | 13.60 | 60.80 | 74.30 | 74.90 | 13.70 |
9 | 151.30 | 128.10 | 10.80 | 74.50 | 13.60 | 60.90 | 74.30 | 75.00 | 13.70 |
10 | 150.30 | 127.10 | 10.80 | 74.60 | 13.50 | 61.10 | 74.50 | 75.10 | 13.70 |
11 | 150.20 | 127.00 | 10.80 | 74.70 | 13.60 | 61.10 | 74.60 | 75.20 | 13.70 |
12 | 151.00 | 127.80 | 10.80 | 74.60 | 13.70 | 60.90 | 74.50 | 75.30 | 13.80 |
13 | 151.50 | 128.30 | 10.80 | 74.70 | 13.60 | 61.10 | 74.60 | 75.20 | 13.70 |
14 | 151.80 | 128.60 | 10.80 | 74.70 | 13.50 | 61.20 | 74.60 | 75.20 | 13.60 |
15 | 151.30 | 128.10 | 10.80 | 74.70 | 13.60 | 61.10 | 74.60 | 75.20 | 13.70 |
16 | 151.50 | 127.90 | 11.20 | 74.60 | 13.60 | 61.00 | 74.50 | 75.30 | 13.70 |
17 | 161.00 | 128.90 | 19.70 | 74.50 | 14.10 | 60.40 | 74.40 | 75.20 | 14.20 |
18 | 163.00 | 130.20 | 20.40 | 74.50 | 14.20 | 60.30 | 74.40 | 75.20 | 14.40 |
19 | 163.10 | 130.20 | 20.50 | 74.50 | 14.60 | 59.90 | 74.40 | 75.20 | 14.50 |
20 | 163.10 | 130.20 | 20.50 | 74.60 | 14.50 | 60.10 | 74.50 | 75.30 | 14.50 |
21 | 163.10 | 130.10 | 20.60 | 74.90 | 14.50 | 60.40 | 74.70 | 75.50 | 14.60 |
22 | 162.70 | 129.70 | 20.60 | 75.00 | 14.50 | 60.50 | 74.80 | 75.50 | 14.70 |
23 | 162.20 | 129.20 | 20.60 | 74.90 | 14.40 | 60.50 | 74.80 | 75.60 | 14.60 |
24 | 162.20 | 129.20 | 20.60 | 75.00 | 14.40 | 60.60 | 74.90 | 75.60 | 14.60 |
|
AVG | 154.80 | 128.46 | 13.95 | 74.49 | 13.79 | 60.70 | 74.38 | 75.09 | 13.90 |
|
MAX | 163.10 | 130.20 | 20.60 | 75.00 | 14.60 | 61.20 | 74.90 | 75.60 | 14.70 |
MIN | 148.30 | 126.90 | 9.00 | 73.80 | 13.30 | 59.90 | 73.80 | 74.50 | 13.40 |
|
Powerhouse 1 |
Powerhouse 2 |
Project |
Hour | Generation Flow kcfs | Forebay Elevation | Forebay Elevation | Generation Flow kcfs | Spillway Gates in Use | Miscellaneous Flow kcfs |
1 | 10.10 | 74.3 | 74.2 | 116.80 | 7 | 12.4 |
2 | 10.10 | 74.1 | 74.0 | 117.90 | 8 | 12.4 |
3 | 10.20 | 74.1 | 74.0 | 117.30 | 8 | 12.4 |
4 | 10.20 | 74.1 | 74.0 | 117.70 | 8 | 12.4 |
5 | 10.10 | 74.0 | 73.9 | 117.60 | 8 | 12.4 |
6 | 10.20 | 73.8 | 73.8 | 118.00 | 8 | 12.4 |
7 | 10.20 | 74.0 | 73.9 | 118.10 | 8 | 12.4 |
8 | 10.10 | 74.4 | 74.3 | 117.80 | 8 | 12.4 |
9 | 10.20 | 74.5 | 74.3 | 117.90 | 8 | 12.4 |
10 | 10.00 | 74.6 | 74.5 | 117.10 | 8 | 12.4 |
11 | 10.00 | 74.7 | 74.6 | 117.00 | 8 | 12.4 |
12 | 10.00 | 74.6 | 74.5 | 117.80 | 8 | 12.4 |
13 | 10.10 | 74.7 | 74.6 | 118.20 | 8 | 12.4 |
14 | 10.20 | 74.7 | 74.6 | 118.40 | 8 | 12.4 |
15 | 10.10 | 74.7 | 74.6 | 118.00 | 8 | 12.4 |
16 | 10.10 | 74.6 | 74.5 | 117.80 | 8 | 12.4 |
17 | 10.20 | 74.5 | 74.4 | 118.70 | 14 | 12.4 |
18 | 10.30 | 74.5 | 74.4 | 119.90 | 14 | 12.4 |
19 | 10.30 | 74.5 | 74.4 | 119.90 | 14 | 12.4 |
20 | 10.30 | 74.6 | 74.5 | 119.90 | 14 | 12.4 |
21 | 10.30 | 74.9 | 74.7 | 119.80 | 14 | 12.4 |
22 | 10.30 | 75.0 | 74.8 | 119.40 | 14 | 12.4 |
23 | 10.20 | 74.9 | 74.8 | 119.00 | 14 | 12.4 |
24 | 10.20 | 75.0 | 74.9 | 119.00 | 14 | 12.4 |
|
AVG | 10.17 | 74.5 | 74.4 | 118.29 | 10 | 12.4 |
|
MAX | 10.30 | 75.0 | 74.9 | 119.90 | 14 | 12.4 |
MIN | 10.00 | 73.8 | 73.8 | 116.80 | 7 | 12.4 |