US Army Corps of Engineers

Priest Rapids Dam

Thursday November 26, 2020

New Date:

HourTotal Outflow kcfsGeneration Flow kcfsSpill kcfsForebay ElevationTailwater ElevationAverage Head
1 97.90 97.40 0.00 487.18 407.89 79.29
2 98.40 97.90 0.00 487.25 407.92 79.33
3 112.20 111.70 0.00 487.10 409.06 78.04
4 110.60 110.10 0.00 487.02 408.63 78.39
5 102.90 102.40 0.00 487.00 408.52 78.48
6 97.20 96.70 0.00 486.94 408.54 78.40
7 107.20 106.70 0.00 486.80 407.90 78.90
8 102.90 102.40 0.00 486.78 408.41 78.37
9 105.90 105.40 0.00 486.81 409.08 77.73
10 112.80 112.30 0.00 486.79 409.04 77.75
11 123.70 123.20 0.00 486.77 409.75 77.02
12 110.90 110.40 0.00 486.83 409.34 77.49
13 100.80 100.30 0.00 486.93 407.34 79.59
14
15 76.40 76.00 0.00 487.11 406.06 81.05
16 92.00 91.50 0.00 486.97 407.75 79.22
17 97.40 96.90 0.00 486.98 407.73 79.25
18 93.60 93.10 0.00 487.15 407.37 79.78
19
20
21
22
23
24
AVG 102.52 102.02 0.00 486.97 408.25 78.71
MAX 123.70 123.20 0.00 487.25 409.75 81.05
MIN 76.40 76.00 0.00 486.77 406.06 77.02